jomar
Footballguy
wondering if I can get some legal advice from the FBG lawyers here.
backstory: I hired a designer and renovation company to redo my master bathroom. We're going on almost 4 months now (on a 4-6 week project) and I still have some issues outstanding. The bathroom is functioning but the quality of work is incredibly poor. I have told the contractor to fix the issues and they have been back out a few times. They fixed some and left others. At this point, I just want them to never set foot in my house again. I would like to hire another contractor to fix the problems, pay them for it, and then pay whatever is left to the original contractor.
this was a $30,000 remodel, I've paid just over $15k so far so the original contractor is definitely in the red so far. I need at least 3 more things re-done. Can I hire another contractor, pay them $5k for example, and then pay the remaining $10k to the original contractor? or do I have to continue to give the original company opportunities to remedy the situation? if they refuse, then can I tell them to pound sand and find somebody else? what is the courts view on things like this? do I have to pay them the $30k even though the work is obviously bad? I have pictures and documentation should this go to court but would like some guidance before I proceed with my next move. I can provide more details on the shoddy work if necessary.
thanks in advance!
backstory: I hired a designer and renovation company to redo my master bathroom. We're going on almost 4 months now (on a 4-6 week project) and I still have some issues outstanding. The bathroom is functioning but the quality of work is incredibly poor. I have told the contractor to fix the issues and they have been back out a few times. They fixed some and left others. At this point, I just want them to never set foot in my house again. I would like to hire another contractor to fix the problems, pay them for it, and then pay whatever is left to the original contractor.
this was a $30,000 remodel, I've paid just over $15k so far so the original contractor is definitely in the red so far. I need at least 3 more things re-done. Can I hire another contractor, pay them $5k for example, and then pay the remaining $10k to the original contractor? or do I have to continue to give the original company opportunities to remedy the situation? if they refuse, then can I tell them to pound sand and find somebody else? what is the courts view on things like this? do I have to pay them the $30k even though the work is obviously bad? I have pictures and documentation should this go to court but would like some guidance before I proceed with my next move. I can provide more details on the shoddy work if necessary.
thanks in advance!